Every studio’s least favorite question to answer honestly, because the honest answer is "it depends," and nobody likes that answer. So instead of dodging, here are the real ranges from our own project logs, and exactly what moves a project from the fast end to the slow end.
Typical timelines by deliverable
A single packshot of a simple product (a bottle, a box, a mat): 3 to 5 business days from files-received to final image. The modeling is quick; most of the time goes into materials and lighting.
A full Amazon listing set (hero image, 4 to 6 secondary images, infographics): 7 to 14 business days. Infographics add design time on top of rendering time.
A complex technical product (electronics with many parts, assemblies, mechanisms): 10 to 20 business days, mostly because modeling dozens of components accurately takes real hours.
Product animation (15 to 30 second video): 2 to 4 weeks. Animation multiplies render time, a video is 24 to 30 images per second, and every frame gets computed.
What makes projects faster
The single biggest accelerator is clean input files. A STEP file from your manufacturer can save us three or four days of modeling compared to working from photos. Original label artwork instead of photographed labels saves another round of revisions. And a clear brief, we wrote a guide to briefing a rendering studio, routinely cuts a full revision cycle out of the schedule.
What makes projects slower
Almost always one of three things:
- Missing information discovered mid-project. The back of the product was never photographed, the label file is low-resolution, nobody knows the exact dimensions.
- Feedback loops. Every revision round adds 1 to 3 days. Consolidated feedback from one decision-maker is fast; feedback trickling in from four stakeholders over a week is not.
- Scope drift. "While you’re at it, could we also see it in blue?" Usually easy, but easy times six requests is a week.
Can it be rushed?
Sometimes, within reason. Rendering hardware works overnight, and simple scenes can be re-lit quickly. What cannot be compressed is careful modeling, accuracy errors made on day one show up in every image after. If you have a hard launch date, tell the studio on day one and build the schedule backwards from it.
The takeaway
For planning purposes: assume two weeks for a proper listing set, add buffer for revisions, and start earlier than feels necessary. And if you want to test the waters first, our $130 test render typically delivers inside a week, which also tells you exactly how we communicate on deadlines before you trust us with a bigger one.